Thursday, November 29, 2007

Week 2 - Day 3



Lots of earth moving again day.
The garage base is now all scraped out and levelled. The hire digger has broken down in the way of everything and can't be moved.

Wednesday, November 28, 2007

Week 2 - Day 2



The footings are bricked up and it's all taking shape.

Sunday, November 25, 2007

Week 2 - Day 1 - 24 November

Saturday.

Nick got the hump as they grab lorry was here at 8am blocking the track so he had to wait to go to work.

They started to dig out the garage base and I made sausage baps. There is now a lot of mud just about everywhere.

Saturday, November 24, 2007

Week 1 - Day 6


Concrete is in the footings. 9 yards of it!

Friday, November 23, 2007

Week 1 - Day 5




All the footings are dug and inspected ok. There are lots of topsoil and clay piles all over the garden and the new drive is taking shape.

I got stuck in the mud last night so the first job for Nick, Dad and the two builders was to push me and my car out of the quagmire.

Dad told Matthew Spencer today - the car mechanic - that he is going to retire to live in Australia. I have two questions a - hasn't he been retired for 15 years and b - what the hell am I doing hocking myself up to the hilt building him an annexe if he isn't going to be living in it!

Thursday, November 22, 2007

Week 1 - Day 4



The majority of the extension footings were dug out and immediately filled with water. Apparently this water has come from underneath the existing house (!) where they sit under the damp proof course. This is normal.

As well of finishing the footings, they will have to be pumped out today into the ditch before the buildings inspector arrives. Providing this is ok - the concrete is coming tomorrow.

It's nice and muddy everywhere and Nick and I will have to park on the cricket pitch from now on as it's so boggy.

Have just looked at the weather. It's going to be minus 5 on Friday night. GREAT!

Wednesday, November 21, 2007

Week 1 - Day 3




The old garage is now part of the new drive as hard-core and all of the ground is levelled for the new extension.
The big digger is coming today and the footings are being dug out.